Baton Rouge road projects 2026

What Baton Rouge drivers can expect from major road projects in 2026

BATON ROUGE — After years of construction cones, detours and daily commuter frustration, 2026 is shaping up to be a turning point for drivers across the greater Baton Rouge region.

State and local transportation officials say several major road projects in East Baton Rouge, Livingston, Ascension and Tangipahoa parishes are scheduled to be completed (or reach major milestones) by 2026, easing congestion in some of the region’s most heavily traveled corridors.

The projects range from long-awaited interchange overhauls and widening efforts to new roundabouts and bridge replacements designed to improve safety and traffic flow as the metro area continues to grow.

MORE: Louisiana political headlines to watch in 2026

MORE: 2026 looms as a pivotal year across Louisiana sports

Baton Rouge: Long-running projects near the finish line

One of the most anticipated projects nearing completion is the Pecue Lane widening and I-10 interchange in Baton Rouge.

The multi-phase project includes widening Pecue Lane between Perkins Road and Airline Highway, constructing new bridges over Ward’s Creek, and reconfiguring access to Interstate 10 with new ramps. Transportation officials say the final phase remains on track for completion in spring to mid-2026.

Once finished, the project is expected to significantly reduce congestion for commuters traveling between Perkins Road, Airline Highway and I-10, a corridor that has become increasingly congested as development expands south.

While the massive I-10 widening and reconstruction project through Baton Rouge will continue beyond 2026, DOTD officials say drivers will see continued progress next year as additional segments are restored and reconfigured, particularly near long-standing bottlenecks. Motorists should continue to expect alternating lane closures.

The demolition and full rebuild portion of I-10 is not slated to begin until 2028, and the entire project is not expected to be completed until 2031.

Another major project expected to wrap up in 2026 is the Plank Road Restoration Project, which aims to transform one of the city’s most historic corridors. The work includes roadway repaving, new sidewalks and curbs, improved lighting, and upgraded traffic signals.

West Baton Rouge: Intracoastal Bridge Phase II

Another regional project tied closely to Baton Rouge traffic is the Intracoastal Canal bridge replacement on LA-1 in West Baton Rouge Parish.

The new northbound and southbound bridges are designed to improve safety and traffic flow for commuters traveling between Baton Rouge, Iberville Parish and points west.

Phase Two of the project is expected to wrap up in 2026.

Livingston Parish: Juban Road project nearing completion

In Livingston Parish, the long-awaited Juban Road widening project is finally nearing the finish line. The project expands Juban Road from U.S. 190 to Castle Road into a four-lane roadway and includes construction of a two-lane roundabout at the intersection of Juban Road and U.S. 190. The work also features additional lanes, multiple roundabouts and safety upgrades aimed at easing congestion in one of the fastest-growing areas of the parish.

Originally slated for completion in 2021, the project was delayed by COVID-19, supply-chain disruptions and workforce shortages. DOTD officials confirmed it was delayed again this year due to utility relocation issues.

Beyond Juban Road, Livingston Parish plans to continue its road overlay and patching program across numerous parish roadways. Parish President Randy Delatte has made infrastructure improvements a central priority, with the work expected to continue into 2026 using parish funds.

Delatte said the parish plans to invest approximately $80 million in road projects in 2026, significantly increasing its typical annual workload.

“Normally, we do about six road projects a year at roughly $8 million each,” Delatte told UWK. “We brought in a professional management group. We never had that before.” They’re going to manage (the projects).”

Ascension Parish: Roundabouts & corridor planning continues

In Ascension Parish, a new roundabout at Parker Road and Joe Sevario Road is under construction and expected to be completed in spring 2026. Local leaders say the project is aimed at reducing crash risks and improving traffic flow at a busy intersection serving rapidly growing residential areas.

The project is the latest in a series of roundabouts across the parish. DOTD completed a $53.2 million widening and roundabout project along LA 70 in Ascension and St. James parishes in December.

Parish leaders also celebrated the opening of the first of three roundabouts on LA 30 in October. Construction will continue in the area, with work now shifting to the LA 30/I-10 interchange ramps. The project includes one roundabout on both the eastbound and westbound sides of the interstate and remains on schedule for completion by mid-2026.

Ascension Parish is also poised for future work along the LA 44 corridor, where widening and improvement projects are advancing through planning and early development stages. While construction may extend beyond 2026, officials say the coming year will be critical in laying the groundwork for long-term congestion relief between I-10 and LA 22.

Download theUnfiltered with Kiranapp from theApple App StoreandGoogle Playto stay updated on the latest news across the Capital area. 

Support UWK and its mission to deliver The News You Deserve. Unfiltered. Become amonthly patron on Patreon today!

Leave a Reply

Your email address will not be published. Required fields are marked *

Interested in advertising with us?

We’d love to have you on the team! Drop us a line and we’ll be happy to follow up. 

Categories

Let's Connect

Follow along on your favorite social media platform and get the latest updates directly in your feed!

Submit a Tip

Have a tip on a story? Send it directly to our team using the form below!
Search