Juban Road construction

When will Juban Road construction end? Officials say finish line is near

DENHAM SPRINGS — If construction on Juban Road has tested your patience, you’re not alone. But the light at the end of the tunnel may finally be in sight.

The project expands Juban Road from U.S. 190 to Castle Road into a four-lane roadway and includes the construction of a two-lane roundabout at the intersection of Juban Road and U.S. 190.

State Sen. Valarie Hodges, who represents Louisiana’s District 13, says a new report from the Louisiana Department of Transportation and Development shows the project reaching “substantial completion” this month.

“Traffic should be moving through the main circle in its final configuration by next week,” Hodges said in a January 7 Facebook post. “Weather, the holidays and cold temperatures slowed progress last month, but DOTD crews are back on the last section near the circle and continuing to push forward.”

Juban construction blame game

Hodges also echoed the frustration of many in her district, adding, “It’s INCONCEIVABLE that it has taken this contractor so incredibly long to do less than two miles of road.”

UWK previously reported in September that unforeseen circumstances, many outside of DOTD’s control, delayed the already behind-schedule project.

MORE: What Baton Rouge drivers can expect from major road projects in 2026

MORE: Utility relocations the source of Juban Road project delays, not ‘lackadaisical efforts’

“What happened with this project is it took almost three years for the utilities to move their stuff,” DOTD communication Diretor Rodney Mallet explained late last year. “So the contractor is in a bind, because he can’t do his job for three years, and he can’t bid on other contracts.”

Mallet said a contractor won the bid for the Juban Road roundabout project in 2018 and began early work known as “clearing and grubbing,” which involves removing trees, stumps and underground utilities to prepare the site for construction.

However, Mallet said the responsibility for relocating utilities, including phone, gas, cable, water and sewer lines, falls on individual utility companies, not the project’s contractor. Construction could not move forward until those utilities were relocated.

MORE: Target officially purchases Livingston Parish property

Juban Road project already improving traffic

Complicating matters further, the COVID-19 pandemic occurred during the utility delays, triggering supply-chain issues and soaring costs. DOTD ultimately combined the roundabout and road-widening projects into a single project in late 2022, with major construction beginning in early 2023.

That work then revealed drainage issues that had not been previously identified.

“I understand it’s been a big pain, Mallet told UWK. “But it’s not because of anything that any one person has done, and it’s not because of any lackadaisical effort.”

Although the project is not yet fully complete, Mallet noted in September that the roundabout has already improved traffic flow, even during times when crashes on Interstate 12 divert vehicles onto Florida Boulevard.

“I appreciate everyone’s patience; it’s going to be a great project,” Mallet said.

  • Juban Road expansion
  • Juban Rd. widening project
  • Juban Road Construction Update April 29, 2025

Download the Unfiltered with Kiran app from the Apple App Store and Google Play to stay updated on the latest news across the Capital area. 

Leave a Reply

Your email address will not be published. Required fields are marked *

Interested in advertising with us?

We’d love to have you on the team! Drop us a line and we’ll be happy to follow up. 

Categories

Let's Connect

Follow along on your favorite social media platform and get the latest updates directly in your feed!

Submit a Tip

Have a tip on a story? Send it directly to our team using the form below!
Search